Asbestos and Demolition - Phase 2 (of 5) development project

October 2, 2016

house demolition process
First of four homes slated for demo for this development.

There are four homes coming down as part of the next phase of this expanding development of modern homes in the western communities. We have provided hazardous materials surveys and a mixture of high and moderate risk work (as required) on a very tight timeline to get this first house ready for demolition.

The entire work area is containing (ie sealed in plastic). The plaster ceiling had to be removed and we also needed to open up the baseboard area to clear debris.  You can also see below the 3 stage decontamination enclosure where workers enter and exit the contained work area (note this includes a shower out facility that all workers, bagged waste, tools, etc most use before exiting).

asbestos decon
3 stage decon with shower
removal of plaster and lathe
Windows get sealed off with poly for high risk work and you can see a separate opening as a viewing window allowing people outside to view work in progress.

Got Questions?

We understand the stress, and confusion that dealing with hazardous materials brings. We're here to help. Got questions? Concerns? or just need to vent (pun intentional) - give us a shout!
Get in Touch

More About What We Do

Member Profile
Member Profile
Certified Asbestos Inspectors
Healthcare Construction
Certificate of Recognition
Better Business Bureau
BC Environment Ind. Association
Power System Safety Protection
AHERA® Certified
We maintain a respectful workplace environment. Ethical, Experienced, & Insured
Canadian HAZ-MAT Environmental Ltd.
Located at 3388 Douglas St. Victoria, BC V8Z 3L3 - All mail to 1111 Tulip Ave, Victoria, BC V8Z-7Z2Site Designed, Developed, & Promoted by MullerConsulting
menuchevron-down